Timeline/Schedule
Spring, 2014 |
Port of Miami Tunnel is completed
|
Fall, 2011
|
Tunnel Boring Machine arrives in Miami for assembly, and tunnel construction begins
|
Spring, 2010 |
Construction begins
|
Oct. 15, 2009 |
FDOT reaches financial close/ Notice to Proceed
|
June 2, 2009 |
FDOT reaches commercial close
|
May 2, 2007 |
FDOT announces intent to select “Best Value Proposer” Miami Access Tunnel team
|
March 5, 2007 |
FDOT receives proposals from short-listed proposers
|
Nov. 1, 2006 |
FDOT publishes a Request for Proposals (RFP) for short-listed proposers
|
April 28, 2006 |
FDOT announces short-list of qualified proposers.
|
April 12, 2006 |
FDOT receives Statement of Qualifications (SOQ) from potential proposers
|
Feb. 17, 2006 |
FDOT publishes a Request for Qualifications (RFQ) from proposers seeking to develop, design, construct, finance, operate and maintain the Port of Miami Tunnel Project through a Concession Agreement
|
|